West Milton to Eldean

The West Milton to Eldean project is a planned 17 mile, 138-kV transmission line that will run from the existing West Milton and Eldean substations near Troy, OH. The project is being planned to ensure reliability in the region and to comply with mandatory NERC standards. The new line will be installed on single wood poles mostly through existing right-of-way. The project is expected to be completed 2022.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Dayton Power and Light 16.7 138 OH OH 2022
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
12.9 Single Planned West Milton Eldean
Interstate Build Start NERC ISO/RTO Country Project Partners
No 2021 RFC PJM US