Tesla to Riley

The Tesla to Riley project is a 66-mile double-circuit 345-kV CREZ transmission line currently under construction between the Tesla Substation near Childress Texas to the Riley Substation near Vernon Texas. Construction began in May 2012 and was completed in June 2013.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Electric Transmission Texas LLC 66 345 TX TX 2013
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
131.6 Operating CREZ Tesla Riley
Interstate Build Start NERC ISO/RTO Country Project Partners
2012 TRE ERCOT US