The Stiles to Coates 138-kV Project involves a new 7.1-mile, 138-kV transmission line as well as a new Coates substation. The new line will accommodate load growth in the Stanton service area mostly due to increased oil and gas activities. The project has an estimated cost of $18.4m and is expected to be completed by fall 2018.