The South Anthony – Lakeside project involves rebuilding an existing 34.5-kV transmission line to 69-kV standards. The rebuild also involves retiring the Lakeside substation. The $10m project is needed to ensure reliability and is expected to be completed in 2020.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Indiana Michigan Power Co. 2 69 IN IN 2020
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
10 Planned Anthony Substation Stormwater Substation
Interstate Build Start NERC ISO/RTO Country Project Partners
2019 RFC MISO US