Scurry County South to Long Draw Line

The Scurry County South to Long Draw Line project is 50.7 miles of two 345 kV circuits sharing common towers. The estimate cost of the project was projected at $96.4 million. Construction began in January 2012 and was completed in September 2013.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Wind Energy Transmission Texas LLC 51 345 TX TX 2013
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
96.4 Operating CREZ Scurry County South Long Draw
Interstate Build Start NERC ISO/RTO Country Project Partners
2012 TRE ERCOT US