The Palmas to East Rio Hondo project involves a new 138-kV, 6.6 mile transmission line to connect the planned Palmas Wind Energy Project to the ERCOT grid. The project has an estimated cost of $11.1m and is expected to be completed by fall 2019.
Project Sponsor | Line Miles | Voltage (kV) | From State | To State | Year in Service |
---|---|---|---|---|---|
South Texas Electric Coop Inc. | 6.6 | 138 | TX | TX | 2019 |
Estimated Costs ($M) | Voltage Type | Project Status | Project Group | Origin Point | Destination Point |
11.1 | Planned | Palmas Altas Wind | East Rio Hondo | ||
Interstate | Build Start | NERC | ISO/RTO | Country | Project Partners |
2019 | TRE | ERCOT | US |