Northeast Renewable Link

The Northeast Renewable Link will deliver up to 600MW of renewable energy to Massachusetts. The new 23-mile, 345-kV line will be built adjacent or within existing right-of-way from National Grid’s Alps substation to Eversource’s Berkshire substation. The $400m project is expected to be completed late 2021.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
National Grid USA 23 345 NY MA 2021
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
400 Planned Alps Berkshire
Interstate Build Start NERC ISO/RTO Country Project Partners
2020 NPCC NYISO US Eversource