The New Buffalo Area Improvements Project involves rebuilding an existing 69-kV transmission between the Bossermand and New Buffalo substations.The project is needed to ensure reliability in the region and is expected to be energized spring 2020.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Indiana Michigan Power Co. 7 69 IN MI 2020
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
27 Planned Bosserman Substation New Buffalo
Interstate Build Start NERC ISO/RTO Country Project Partners
RFC MISO US