Moses-Adirondack Smart Path Reliability Project

The Moses – Adirondack Smart Path Reliability Project involves replacing two existing 86 mile transmission lines in Lawrence and Lewis County, NY. The lines will be rebuilt to 345-kV standards but continue to operated at 230-kV. When completed, the project will allow new renewable capacity from upstate New York to be carried to high demand regions downstate.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
New York Power Authority 86 345 NY NY 2023
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
668.7 Single Planned Moses Adirondack
Interstate Build Start NERC ISO/RTO Country Project Partners
No 2020 NPCC NYISO US