The Moreau to Greenwich Rebuild project is a planned upgrade of two existing 115-kV transmission lines between Moreau and Greenwich. The project is being proposed to address the grid reliability in the region and protect demand development. Construction is expected to begin in late 2014.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
National Grid USA 14 115 NY NY 2015
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
31 Suspended Moreau Greenwich
Interstate Build Start NERC ISO/RTO Country Project Partners
NPCC NYISO US