Lamping to Rouse 138 kV Transmission Line Project

The Lamping to Rouse 138-kV Transmission Line Project involves a new 4.8-mile line in Monroe County, OH. The project is being proposed to improve reliability in the region and is expected to be completed by late 2019.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
AEP Ohio 4.8 138 OH OH 2019
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
7.5 Planned Lamping Substation Rouse Substation
Interstate Build Start NERC ISO/RTO Country Project Partners
2018 RFC PJM US