Kathleen to Zephyrhills North

Duke Energy has built a 13 mile transmission line from its existing Kathleen substation to the Zephyrhills North substation. The addition of the Kathleen to Zephyrhills North line will ensure improved reliability and provide redundancy in the region. Construction began fall 2012 and was completed in September 2013.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Progress Energy Florida Inc. 13 230 FL FL 2013
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
20.8 Operating Kathleen Zephyrhills North
Interstate Build Start NERC ISO/RTO Country Project Partners
2012 FRCC US