The Huntington Area Improvements Project involves a new 3-mile, single circuit 138-kV transmission line in Huntington, WV. The $25m project is needed to ensure reliability in the region. Appalachian power expects to complete the line mid-2019.
The Huntington Area Improvements Project involves a new 3-mile, single circuit 138-kV transmission line in Huntington, WV. The $25m project is needed to ensure reliability in the region. Appalachian power expects to complete the line mid-2019.
Project Sponsor | Line Miles | Voltage (kV) | From State | To State | Year in Service |
---|---|---|---|---|---|
Appalachian Power Co. | 3 | 138 | WV | WV | 2019 |
Estimated Costs ($M) | Voltage Type | Project Status | Project Group | Origin Point | Destination Point |
25 | Single | Under Construction | East Huntington | Darrah | |
Interstate | Build Start | NERC | ISO/RTO | Country | Project Partners |
No | 2018 | RFC | PJM | US |