Greenville to Kinston Dupont

Duke Energy Progress plans to invest about $20 million to build a 25-mile, 230-kilovolt (kV) transmission line between a substation near the Tar River in Greenville and a substation south of Grifton, just inside the Lenoir County line.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Duke Energy Corporation 25 230 NC NC 2015
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
20 Operating Tar River, NC Grifton, NC
Interstate Build Start NERC ISO/RTO Country Project Partners
2014 SERC US