East Abilene to Putnam

East Abilene to Putnam is a 32-mile, 138-kV transmission line, originating at East Abilene and terminating at Putnam, Texas. Built by Electric Transmission Texas LLC, the transmission line cost $15.2 million and enables greater renewable energy delivery, reliability and system stability.The line was placed in service on June 19, 2012.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Electric Transmission Texas LLC 32 138 TX TX 2012
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
15.2 Operating CREZ East Abilene Putnam
Interstate Build Start NERC ISO/RTO Country Project Partners
2011 TRE ERCOT US