DeWitt – Tilden Conductor Clearance Refurbishment Project

The DeWitt-Tilden Conductor Clearance Refurbishment Project is a planned 7.5 mile, 115-kV transmission line which will run from the Dewitt substation in Dewitt, NY, to the Tilden substation in Onondoaga, NY. The line will be built on single circuit wood H-frame structures and is needed to ensure system reliability in the region.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
National Grid USA 7.5 115 NY NY 2015
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
7.5 Operating Dewitt Substation Tilden
Interstate Build Start NERC ISO/RTO Country Project Partners
No 2014 NPCC NYISO US