Dermott to Scurry County South

Dermott to Scurry County South is a 33-mile, 345-kV transmission line, originating at Dermott Collection Station and terminating at Scurry County South Collection Station in Scurry County, Texas. Proposed by Oncor Electric Delivery Co., the transmission line cost $49 million and was energized on December 1, 2011. The project will interconnect renewable energy from the Central CREZ Zone to lines serving North and Central Texas. Also, the project is critical to relieve the congestion that is hampering the delivery of existing wind-energized energy to the grid.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Oncor Delivery Company LLC 33 345 TX TX 2011
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
49 Operating CREZ Dermott Collection Station Scurry County South Collection Station
Interstate Build Start NERC ISO/RTO Country Project Partners
2011 TRE ERCOT US