The Dent Road Expansion to Wieland Switch 138-kV Transmission Line involves a new 6.85 to 10.9 mile line from the existing Dent Road substation to a proposed Wieland switching station.. The project is being built to improve reliability in Wieland, TX. Rayburn Country Electric Cooperative expects to complete the line in 2019 at a cost of approximately $6.6m.