Cloverdale Expansion Project

The Cloverdale Expansion Project will be built near the existing Cloverdale substation and includes three new 345-kV transmission lines and one new 500-kV transmission line; the partial relocation of an existing 765-kV transmission line, an existing 500-kV transmission line and two existing 138-kV transmission lines; and improvements to the Cloverdale substation, including the construction of a new 500-kV yard to serve as the terminus for the relocated 500-kV line. Construction began in March 2015, while this project is expected to be completed by summer 2017.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Appalachian Power Co. 4.7 345 VA VA 2017
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
237 Operating Cloverdale Cloverdale Substation East Yard
Interstate Build Start NERC ISO/RTO Country Project Partners
No 2015 SERC PJM US