Clear Crossing to Dermott is a 90-mile, double-circuit 345-kV transmission line that originates at Clear Crossing northeast of Stamford, Texas and terminates at Dermott Substation in northwest Dickens County, Texas. The transmission line, sponsored by Electric Transmission Texas LLC, had a baseline cost estimate of $189.2 million. Construction began in April 2012 and was completed in October 2013.