The Central South Bend Reliability Project involves a new 2-mile, 69-kV underground transmission line between a new Muessel and Rapids substation. The project is crucial to improve reliability in the region.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
Indiana Michigan Power Co. 2 69 IN IN 2019
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
20 Planned Muessel Substation Colfax Substation
Interstate Build Start NERC ISO/RTO Country Project Partners
2018 RFC MISO US