The Central South Bend Reliability Project involves a new 2-mile, 69-kV underground transmission line between a new Muessel and Rapids substation. The project is crucial to improve reliability in the region.
The Central South Bend Reliability Project involves a new 2-mile, 69-kV underground transmission line between a new Muessel and Rapids substation. The project is crucial to improve reliability in the region.
Project Sponsor | Line Miles | Voltage (kV) | From State | To State | Year in Service |
---|---|---|---|---|---|
Indiana Michigan Power Co. | 2 | 69 | IN | IN | 2019 |
Estimated Costs ($M) | Voltage Type | Project Status | Project Group | Origin Point | Destination Point |
20 | Planned | Muessel Substation | Colfax Substation | ||
Interstate | Build Start | NERC | ISO/RTO | Country | Project Partners |
2018 | RFC | MISO | US |