The Cedar Lake project involves a new 4.5-mile, 115-kV transmission line in Scott County, MN. The project is needed to serve a new pipeline pump station proposed by Minnesota Pipe Line Company.
The Cedar Lake project involves a new 4.5-mile, 115-kV transmission line in Scott County, MN. The project is needed to serve a new pipeline pump station proposed by Minnesota Pipe Line Company.
Project Sponsor | Line Miles | Voltage (kV) | From State | To State | Year in Service |
---|---|---|---|---|---|
Great River Energy | 4.5 | 115 | MN | MN | 2017 |
Estimated Costs ($M) | Voltage Type | Project Status | Project Group | Origin Point | Destination Point |
5 | Operating | Cedar Lake Substation | MV-EV/X Transmission Line | ||
Interstate | Build Start | NERC | ISO/RTO | Country | Project Partners |
2017 | MRO | MISO | US |