The Burrillville Interconnection Project is a proposed 6.8 mile, 345-kV transmission line that would connect the planned Clean River Energy Center to National Grid’s electrical system. Most of the line will be located withing existing right-of-way with an estimated cost of $47.2m. The project is expected to be completed by the end of 2020.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
National Grid USA 6.8 345 RI RI 2020
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
47.2 Planned Sherman Road Switching Station Clear River Energy Center
Interstate Build Start NERC ISO/RTO Country Project Partners
2018 NPCC ISONE US