The Bee Branch to Damascus Rebuild involves replacing 7.1 miles of existing 161-kV transmission line. The project is needed to ensure reliability in the region.
The Bee Branch to Damascus Rebuild involves replacing 7.1 miles of existing 161-kV transmission line. The project is needed to ensure reliability in the region.
Project Sponsor | Line Miles | Voltage (kV) | From State | To State | Year in Service |
---|---|---|---|---|---|
Petit Jean Electric Cooperative | 7.1 | 161 | AR | AR | 2017 |
Estimated Costs ($M) | Voltage Type | Project Status | Project Group | Origin Point | Destination Point |
6.6 | Operating | Bee Branch | Damascus Substation | ||
Interstate | Build Start | NERC | ISO/RTO | Country | Project Partners |
2017 | SERC | US |