Barnesville – Summerfield Rebuild

The Barnesville – Summerfield Rebuild involves replacing about 16-miles of aging power lines in Noble County, OH. The existing 69-kV lines would be updated with 138-kV lines to meet increased demand. The project has an estimated cost of $32.6m with a completion date of late 2018.

Project Sponsor Line Miles Voltage (kV) From State To State Year in Service
AEP Ohio 16 138 OH OH 2018
Estimated Costs ($M) Voltage Type Project Status Project Group Origin Point Destination Point
20 Under Construction Barnesville Summerfield
Interstate Build Start NERC ISO/RTO Country Project Partners
2017 RFC PJM US