ATC: Actual project cost as of March 31 was about $30.6m on Boscobel to Lone Rock project

ATC said that the rebuild of Y124 is substantially complete and that a 1.7-mile segment of Y124 remains to be rebuilt in coordination with the Muscoda Utilities expansion of its industrial substation