PJECC: 161-kV transmission line in Arkansas completed

Petit Jean Electric Cooperative Corporation (PJECC) on Dec. 27, 2018, filed with the Arkansas Public Service Commission a report of project completion regarding the construction of 161-kV transmission facilities.

As TransmissionHub reported, the commission, in a May 2017 order, said that there being no further action to be taken at this time concerning PJECC’s proposed 7.1-mile, 161-kV transmission line, the commission secretary is to close the docket (Docket No. 16-051-U).

As noted on the APSC’s website, the last action taken in the matter prior to the May 2017 order occurred in March when an administrative law judge (ALJ) granted PJECC a certificate of public convenience and necessity (CCN) to build, operate, and maintain the project.

According to that March 1, 2017, order, PJECC in July 2016 filed an application with the APSC seeking a CCN to build, own, and operate a line from PJECC’s existing Bee Branch substation, and running south, then west, to PJECC’s new Damascus substation. PJECC in November 2016 filed an amendment to the application, amending the proposed route of the proposed line, referred to in the order as the “Amended Proposed Route,” or “Alternative 1.”

As noted in the March 1 order, the proposed line and new Damascus substation are needed to provide service to a new 5,000-kW large power customer, relieve substation loading, provide for proper voltage, and improve reliability in the Bee Branch and Quitman substation areas.

According to PJECC, the load imposed on the Bee Branch substation is expected to exceed the station’s ratings in 2018 under extreme winter weather conditions, and the Quitman substation is expected to reach about 90% of its maximum load rating during the same time frame. According to PJECC, those high load levels can damage substation equipment if an overload occurs, as well as limit the cooperative’s ability to backfeed one substation from another during outages, reducing area reliability.

PJECC also said that with the loads expected under extreme winter weather conditions, analysis indicates that several circuits in the Bee Branch and Quitman substations will have voltage drops in excess of the Rural Utility Service (RUS) limits, and without the addition of the Damascus substation, significant distribution upgrades would be needed to bring the forecast voltage drops to within RUS-established limits.

As originally proposed, the March 1 order added, the line’s route would originate at the Bee Branch substation and parallel an existing transmission line in a southeasterly direction for about 0.6 miles, at which point it turns south for about 4.4 miles, with a few minor variations to avoid certain property uses, but generally following property boundaries. At that point, the route turns southwest for about 0.6 miles, meeting U.S. Highway 65, and continuing parallel to Highway 65 on the westward side for another mile, then turning west about 0.5 miles to terminate at the Damascus substation. The amendment filed last November to the proposed route includes a minor change at the point where the route turns west, leaving Highway 65 to terminate at the Damascus substation.

According to PJECC, the amended proposed route avoids a residential property by moving the line to traverse between two commercial properties, adding about 300 feet to the route. The March 1 order also noted that the amended proposed route reduces the amount of new disturbed land by using an existing distribution line easement for the part of the amended route.

In its Dec. 27, 2018, filing, PJECC said that the project construction, electrical testing, and final energization of the electric facilities have been completed by the contractor, Global Energy Services, Inc., and the transmission line was turned over to the owner, PJECC, on April 12, 2018.

The transmission construction portion was completed in accordance with the CCN granted by the commission, with no deviations in line routing required. The final record length of the line is 7.23 miles, PJECC added, noting that the estimated cost of the Bee Branch-Damascus 161-kV Transmission Line was $6.6m, and that the final cost of the project was about $7.5m – that is, about $5.7m for the total transmission cost and about $1.9m for the total Damascus substation cost.

About Corina Rivera-Linares 3059 Articles
Corina Rivera-Linares, chief editor for TransmissionHub, has covered the U.S. power industry for the past 15 years. Before joining TransmissionHub, Corina covered renewable energy and environmental issues, as well as transmission, generation, regulation, legislation and ISO/RTO matters at SNL Financial. She has also covered such topics as health, politics, and education for weekly newspapers and national magazines. She can be reached at clinares@endeavorb2b.com.