ATSI: Public informational meeting scheduled for Sept. 26 regarding 138-kV project

FirstEnergy’s (NYSE:FE) American Transmission Systems, Incorporated (ATSI) on Aug. 28 said that a public informational meeting for the proposed Wood County 138-kV Reinforcement Project will be held on Sept. 26 in Bowling Green, Ohio.

As noted in the Aug. 28 pre-application notification letter that ATSI filed with the Public Utilities Commission of Ohio, the project involves improvements to the transmission and sub-transmission systems in Wood County, Ohio.

If approved and built, the project would result in improvements to the resiliency, overall efficiency, and operational flexibility of those systems, the company said.

The project – which would be located in northwestern Wood County – involves a new approximately 5.5-mile line extending from the existing Lemoyne-Midway 138-kV Transmission Line to the existing Brim substation. The company added that route alternatives under consideration traverse Middleton, Center, and Plain townships, as well as a portion of the City of Bowling Green.

ATSI said that it will file an application for a certificate of environmental compatibility and public need for the proposed line in mid-December, and that it plans to file a letter of notification application at a later date for the related proposed expansion of the Brim substation to support the project.

About Corina Rivera-Linares 3286 Articles
Corina Rivera-Linares was TransmissionHub’s chief editor until August 2021, as well as part of the team that established TransmissionHub in 2011. Before joining TransmissionHub, Corina covered renewable energy and environmental issues, as well as transmission, generation, regulation, legislation and ISO/RTO matters at SNL Financial from 2005 to 2011. She has also covered such topics as health, politics, and education for weekly newspapers and national magazines.