ATC provides update on Boscobel to Lone Rock project in Wisconsin

American Transmission Company (ATC) on July 20 filed with the Public Service Commission of Wisconsin a quarterly progress report for the period April 1 through June 30 for the Boscobel to Lone Rock (Line Y124) Rebuild Project, noting that the project is on schedule for a December 2019 in-service date.

As TransmissionHub reported, the commission, in a September 2016 final decision, granted, subject to conditions, ATC’s application for authority to rebuild about 25 miles of the existing 69-kV transmission line between the existing Boscobel substation in the city of Boscobel, Grant County, and the Lone Rock substation in the town of Buena Vista, Richland County.

Other than rerouting the line in two segments for a total distance of about nine miles, the existing line will be rebuilt within its existing right of way, the commission said in its decision.

The operating voltage of the line will remain at 69 kV, the commission said. ATC proposes to rebuild about 25 miles of the existing 27.6-mile line, the commission said, adding that the company and its predecessor transmission owner have performed maintenance rebuilding on the remaining 2.6 miles of the line during the past 20 to 30 years. On that section of the line, ATC proposes to selectively replace additional facilities following regular maintenance inspections, the commission said.

As part of the proposed project, ATC will install an optical ground wire for information and protection purposes for the entire 27.6-mile length of the line, the commission said. In areas that will be completely rebuilt, the existing wood pole wishbone structures will be replaced by weathering steel monopole structures, the commission said.

Discussing the project’s need, the commission noted that the line was originally built in 1955, and is about 61 years old. The line is in poor physical condition and is reaching the end of its useful life, the commission said.

In its July 20 progress report, ATC said that an incidental take authorization (ITA) application was submitted to the Wisconsin Department of Natural Resources Bureau of Natural Heritage Conservation in June.

Detailed design activities for the transmission line portion of the project continue, while detailed design activities on the substation portion have not started, the company said.

Actual project costs as of June 30 were about $2.3m, out of the approved total project cost of about $32.4m, ATC said.

About Corina Rivera-Linares 3054 Articles
Corina Rivera-Linares, chief editor for TransmissionHub, has covered the U.S. power industry for the past 15 years. Before joining TransmissionHub, Corina covered renewable energy and environmental issues, as well as transmission, generation, regulation, legislation and ISO/RTO matters at SNL Financial. She has also covered such topics as health, politics, and education for weekly newspapers and national magazines. She can be reached at clinares@endeavorb2b.com.