Revised interconnect deal filed for 89-MW Cottonwood Wind project in Nebraska

The Southwest Power Pool on Nov. 14 filed with the Federal Energy Regulatory Commission an executed Generator Interconnection Agreement (GIA) with Cottonwood Wind Project LLC and interconnecting transmission owner Nebraska Public Power District.

This Fifth Revised Cottonwood GIA modifies and supersedes the GIA among the parties that the commission accepted on Nov. 10, 2015. 

Cottonwood plans to construct an 89.48 MW wind generation facility, which will consist of forty-eight (48) General Electric 1.715 MW wind turbines and four General Electric 1.79 MW wind turbines. Since the GIA from last November, the parties agreed to update the Appendix B milestones.

The project’s Point of Interconnection is NPPD‘s new Rosemont 115-kV substation, to be located on the Pauline-Guide Rock 115-kV transmission line.

The current commercial operation target date is Dec. 1, 2017.

A project contact is: Sam Massey, Project Director, Cottonwood Wind Project LLC. c/o NextEra Energy Resources, FEW/JB, 700 Universe Blvd, Juno Beach, FL 33408, Phone:(415) 318-5912, sam.massey@nexteraenergy.com.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.