MISO files preliminary agreement for 340-MW MidAmerican wind project in Iowa

The Midcontinent Independent System Operator filed with the Federal Energy Regulatory Commission on Sept. 2 an Agreement for Preliminary Engineering Design, Permitting and Procurement of Material with MidAmerican Energy as both the interconnecting transmission owner and the developer of a 340-MW wind project in Iowa.

MISO has designated this as Project No. J498 in its interconnection queue.

This wind farm will be located in Boone and Greene counties, Iowa, and will consist of 170 wind turbines rated at approximately 2 MW each with a total output of 340 MW (net) of Energy Resource Interconnection Service and/or Network Resource Interconnection Service.

MidAmerican as transmission owner agreed to use reasonable efforts to complete the work to support the following interconnection schedule:

  • Sept. 4, 2017 Transmission Owner Network Upgrades and Interconnection Facilities In-Service Date (“Backfeed Date”);
  • Sept. 4, 2017 – Generating Facility Testing Date; and
  • Dec. 15, 2017 – Generating Facility Commercial Operation Date.

This facility is currently expected to interconnect with the 345 kV transmission system owned by MidAmerican and operated by MISO in accordance with the MISO Open Access Transmission, Energy and Operating Reserve Markets Tariff.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.