CleanLight pursues interconnect for 13-MW Maryland solar project at PJM

CleanLight Power + Energy LLC has proposed a solar facility located in Garrett County, Maryland, with a total capability of 13 MW, with 4.9 MW of this output being recognized by PJM Interconnection as capacity

PJM said in a September 2016 study on the project that the proposed in-service date is Dec. 15, 2016. This study does not imply a Potomac Edison commitment to this in-service date. This project, under PJM queue #AB1-065, will interconnect with the Potomac Edison transmission system by tapping the Jennings–Hoyes 34.5-kV line.

The intent of this System Impact Study is to determine a plan, with approximate cost and construction time estimates, to connect the subject generation interconnection project to the PJM network at a location specified by CleanLight. It is a mid-point in the PJM queue process.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.