Strata Solar seeks okay on 5-MW Peake Road Farm project in North Carolina

The Peake Road Farm LLC affiliate of Strata Solar LLC applied Aug. 2 to the North Carolina Utilities Commission for a Certificate of Public Convenience and Necessity authorizing construction of a 5-MW (ac) solar facility in Granville County.

The facility site is located on the north side of Peake Road, east of the intersection with Triple Creek Farm Road, and northwest of the intersection with Old NC 75 (also known as State Road 1004), in Oxford, Granville County.

The $14 million facility is projected to come on-line in July 2017. Electricity generated will be sold to Duke Energy Progress under a 15-year power purchase agreement. The service life of the equipment is expected to be a minimum of twenty years. The projected annual sales of the facility are 9,000,000 kWh.

A project contact is: Jackson Naftel, Strata Solar LLC, 50101 Governors Drive, Suite 280, Chapel Hill, NC 27517, 919.960.6015, jnaftel@stratasolar.com.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.