PJM Interconnection on July 15 filed with FERC an executed interconnection service agreement (ISA) with Pivotal Power Solutions Inc. and interconnecting transmission owner Potomac Edison.

This ISA facilitates the interconnection to the PJM transmission system of 9.9 MW (Maximum Facility Output) at the Union Bridge Solar Facility, to be located at 536 Green Valley Road, Union Bridge, Carroll County, Maryland. The ISA indicates that Pivotal Power shall have 3.8 MW of Capacity Interconnection Rights commencing May 31, 2019, at the Point(s) of Interconnection specified in this ISA.

The project is under PJM Queue Position #AB1-096. It is an inverter-based photovoltaic ground-mounted solar generator. On or before Nov. 1, 2017, the developer must demonstrate commercial operation of all generating units.

About Corina Rivera-Linares 3152 Articles
Corina Rivera-Linares, chief editor for TransmissionHub, has covered the U.S. power industry for the past 15 years. Before joining TransmissionHub, Corina covered renewable energy and environmental issues, as well as transmission, generation, regulation, legislation and ISO/RTO matters at SNL Financial. She has also covered such topics as health, politics, and education for weekly newspapers and national magazines. She can be reached at clinares@endeavorb2b.com.