The Federal Energy Regulatory Commission on July 26 granted a December 2015 application from Energy Resources USA Inc. for a preliminary permit allowing it up to three years to study the feasibility of the Rough River Lake Dam Hydroelectric Project, to be located at the U.S. Army Corps of Engineers’ Rough River Lake Dam on the Rough River, in Breckinridge and Greyson counties, Kentucky.

The proposed project would consist of: a control structure with three 9.5-foot-wide, 25-foot-long spill gates, to be built at the end of the existing Corps outlet channel; one 9.5-foot-diameter, 130-foot-long penstock with a butterfly valve; a bifurcation structure; two 6.5-foot-diameter, 32-foot-long penstocks; a powerhouse containing two generating units with a total capacity of 10 MW; a 1,000-foot-long, 220-foot-wide tailrace; a substation; and a 0.3-mile-long, 69-kV transmission line.

The proposed project would have an estimated average annual generation of 8,700 megawatt-hours, and operate as directed by the Corps.

During the course of the permit, the commission expects that the permittee will carry out prefiling consultation and study development leading to the possible development of a license application.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.