78-MW Jericho Rise Wind project in N.Y. to go commercial in November 2016

The New York Independent System Operator and interconnecting transmission owner the New York Power Authority on July 12 filed with the Federal Energy Regulatory Commission an executed Large Generator Interconnection Agreement for the in-construction, 77.7-MW project of Jericho Rise Wind Farm LLC.

Jericho Rise is constructing a 77.7-MW wind farm in Franklin County, New York. The facility will consist of 37 Gamesa G114 2.1-MW turbines. The project will interconnect to certain transmission facilities of NYPA that are part of the New York State Transmission System. The Point of Interconnection will be at the existing 115 kV Willis Substation between the existing 115 kV Breaker 1108 and new 115 kV Breaker 1114.

The project’s commercial operation target date under this LGIA is in November of this year.

A listed project contact is: Jericho Rise Wind Farm LLC c/o EDP Renewables North America LLC, 808 Travis, Suite 700, Houston, TX 77002, Attn: General Counsel Cc: Executive Vice President, Asset Operations.

This project is listed on the website of EDP Renewables.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.