EIA reflects on deployment of TVA Watts Bar 2

When the Tennessee Valley Authority (TVA) connected Watts Bar 2 to the grid June 3, it became the first nuclear power plant to come online since 1996, when Watts Bar Unit 1 started operations, the Energy Information Administration (EIA) said in a June 14 analysis.

Watts Bar Unit 2 is undergoing final testing, producing electricity at incremental levels of power, as TVA prepares to start commercial operation later this summer. The new reactor is designed to add 1,150 MW of electricity generating capacity to southeastern Tennessee.

Watts Bar Unit 2 is the first nuclear plant in the United States to meet new regulations from the Nuclear Regulatory Commission (NRC) that were established after the 2011 earthquake and tsunami that damaged the Fukushima Daiichi Nuclear Plant in Japan, EIA noted.

After the NRC issued an operating license for the unit in October 2015, 193 new fuel assemblies were loaded into the reactor vessel the following month. TVA announced at the end of May that the reactor achieved its first sustained nuclear fission reaction.

Construction on Watts Bar Unit 2 originally began in 1973, but construction was halted in 1985 after the NRC identified weaknesses in TVA’s nuclear program. In August 2007, the TVA board of directors authorized the completion of Watts Bar Unit 2, and construction started in October 2007. At that time, a study found Unit 2 to be effectively 60% complete with $1.7 billion invested. The study said the plant could be finished in five years at an additional cost of $2.5 billion. However, both the timeline and cost estimate developed in 2007 proved to be overly optimistic, as construction was not completed until 2015, and costs ultimately totaled $4.7bn.

EIA also noted that more than three dozen commercial reactors began construction and came online since Watts Bar 2 initially started construction in 1973.

Although Watts Bar 2 is the first new U.S. nuclear generator to come online in 20 years, four other reactors are currently under construction and are expected to join the nuclear fleet within the next four years.

Vogtle Electric Generating Plant Units 3 and 4 being developed in in Georgia by Southern (NYSE:SO) and its partners; and Virgil C. Summer Nuclear Generating Station Units 2 and 3 in South Carolina being developed by SCANA (NYSE:SCG) and Santee Cooper are scheduled to become operational in 2019–20.

The four units together will be adding 4,540 MW of generation capacity, EIA noted.

About Wayne Barber 4201 Articles
Wayne Barber, Chief Analyst for the GenerationHub, has been covering power generation, energy and natural resources issues at national publications for more than 20 years. Prior to joining PennWell he was editor of Generation Markets Week at SNL Financial for nine years. He has also worked as a business journalist at both McGraw-Hill and Financial Times Energy. Wayne also worked as a newspaper reporter for several years. During his career has visited nuclear reactors and coal mines as well as coal and natural gas power plants. Wayne can be reached at wayneb@pennwell.com.