PJM Interconnection on May 18 filed with the Federal Energy Regulatory Commission an executed Wholesale Market Participation Agreement with IMG Development LLC and interconnecting transmission owner Pennsylvania Electric for a 19.9-MW project in Pennsylvania.

“PJM is submitting this Agreement for filing because the Wholesale Market Participant intends to engage in wholesale sales in the PJM markets from a generating facility connected to the Transmission Owner’s distribution facilities,” said the filing.

This project is under PJM Queue Position #AA1-106. It is called the Pine Hill Generating Station, to be located at State Route 414 and Ogdensburg Road, Union Township, Pa. Maximum Facility Output is 19.9 MW It will consist of five 4-MW generators.

On or before Dec. 31, 2017, IMG must demonstrate commercial operation of all generating units.

The project contact information is: Mark Brozina, Managing Director, IMG Development LLC, 301 Oxford Valley Road, Suite 1604, Yardley, PA 19067.

IMG in the last couple of years has been permitting several gas-fired power projects of a similar size in Pennsylvania.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.