PJM Interconnection on Nov. 12 notified the Federal Energy Regulatory Commission of the cancellation of an executed Interconnection Service Agreement (ISA) entered into among PJM, Valley View Spindle LLC (VVS) and interconnecting transmission owner PPL Electric Utilities.

“The VVS ISA is being cancelled because VVS has decided not to move forward with its project and will not participate in PJM’s markets,” PJM told the commission. The ISA had been filed with the commission on Feb. 5 of this year.

The agreement had covered the Valley View Flywheel Station, to have been located in Jessup Borough, Lackawanna County, Pennsylvania. The maximum facility output was to be 20 MW. It would have consisted of flywheels connected through 110-kW inverters. It had been due for commercial operation by the end of 2016.

The company contact information is: Valley View Spindle LLC, 65 Middlesex Road, Tyngsboro, MA 01879.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.