Interconnect deal revised for Apex’s Chapman Ranch Wind I project in Texas

Electric Transmission Texas LLC on Oct. 28 filed a first amendment to a Generation Interconnection Agreement with the Chapman Ranch Wind I LLC affiliate of Apex Clean Energy LLC for a 250-MW wind project.

The original GIA was worked out earlier this year, with the revisions covering several areas of the agreement. The agreement doesn’t call for a specific commercial operation date, with milestones in the deal based on when previous milestones are achieved.

The project will interconnect into the Santa Cruz Substation of Electric Transmission Texas in Nueces County, Texas. This wind farm will have a nominal 250 MW of capacity, and will be made up of 125 Vestas V110 wind turbines, each with a capacity of 2 MW.

Apex Clean Energy says about this project on a website dedicated to the project: “If built, Chapman Ranch will have a capacity of up to 249 MW, producing enough energy to power more than 92,000 homes every year. Representing a private investment well in excess of $300 million, Chapman Ranch Wind will benefit the economy of Nueces County in the near-term with construction jobs and local purchasing of materials and services.  In the long-term, the project promises to bring sustained tax revenue to the County for the local government and schools, as well as 25 years of local purchasing, employment and investment.”

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.