FERC takes comment on competing apps for hydro project on Mississippi River

The Federal Energy Regulatory Commission went out for comment on Oct. 7 on competing preliminary permit applications from Lock+ Hydro Friends Fund X LLC and Energy Resources USA Inc. to study the feasibility of a hydro project, to be located at the existing Mississippi River Lock and Dam No. 24 on the Mississippi River, near the city of Clarksville in Pike County, Missouri, and Calhoun County, Illinois.

Mississippi River Lock and Dam No. 24 is owned by the federal government and operated by the U.S. Army Corps of Engineers. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the three-year permit term.

  • Lock+ Hydro Friends Fund X’s proposed project would consist of: three new 450-foot-wide by 25-foot-deep modular hydropower systems, each containing ten new 1-MW turbine-generator units (30 MW total); a new 200-foot-long by 450-foot-wide tailrace; a new 3-mile-long, 69-kV transmission line; and a new 25-foot by 50-foot switchyard. It would have estimated annual generation of 170,000 megawatthours. The applicant contact is: Wayne Krouse, P.O. Box 43796, Birmingham, AL 35243; (877) 556-6566, extension 709.
  • Energy Resources USA’s project would consist of: a new 770-foot-long by 300-foot-wide intake area; a new 90-foot by 220-foot reinforced concrete powerhouse; four 3-MW turbine-generators (total of 12 MW); a new 1,000-foot-long by 220-foot-wide tailrace area; a new 60-foot-long by 50-foot-wide substation; a new 50-foot-wide by 60-foot-long substation; and a new 5.49-mile-long, 115-kV transmission line. The project would have an estimated annual generation of 102.5 gigawatt-hours. The applicant contact is: Ander Gonzalez, 2655 Le June Road, Suite 804, Coral Gables, FL 33134; +34 93 252 3840.

The deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications is 60 days from the issuance of this Oct. 7 notice.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.