FERC issues notice about Cameron LNG expansion project in Louisiana

The Federal Energy Regulatory Commission on Oct. 13 issued a notice about a Sept. 28 application from Cameron LNG LLC for authority to site, construct, and operate facilities to provide additional natural gas processing, storage, and liquefaction capability at the site of the existing Cameron LNG liquefied natural gas terminal in Cameron and Calcasieu parishes, Louisiana.

The expansion project would increase the Cameron LNG terminal’s maximum natural gas liquefaction and export capabilities from 14.95 to 24.92 million tonnes per annum (MPTA). FERC noted that any questions regarding this application should be directed to Blair Woodward, General Counsel, Cameron LNG LLC, 2925 Briarpark Drive, Suite 1000, Houston, Texas 77042, phone (832) 783-5582, bwoodward@cameronlng.com.

On March 2 of this year, the commission staff granted Cameron LNG’s request to use the pre-filing process, which officially ended as of the filing of the Sept. 28 application.

The construction and operation of these facilities is collectively referred to as the “Cameron LNG Expansion Project.” In 2003, the commission issued to Cameron LNG (formerly Hackberry LNG) authorization to site, construct and operate a liquefied natural gas (LNG) import facility in Cameron Parish, Louisiana (LNG Terminal). The initial maximum send-out rate for the LNG Terminal was 1.5 Billion cubic feet (Bcf) per day.

In 2007, the commission issued another authorization that increased the LNG Terminal’s maximum send-out rate to 1.8 Bcf per day. Cameron LNG completed construction and testing of the LNG Terminal and placed it in service in July 2009. The LNG Terminal has been in continuous operation since that time. Initially, the LNG Terminal was used for the sole purpose of receiving and storing foreign-sourced LNG, and re-gasifying such LNG and sending natural gas out for delivery to domestic markets.

In 2011, the commission authorized Cameron LNG to operate the LNG Terminal for the additional purpose of exporting previously imported (i.e., foreign-sourced) LNG on behalf of its customers. The LNG Terminal has an existing interconnection with Cameron Interstate Pipeline LLC.

In June 2014 the commission authorized Cameron LNG’s “Liquefaction Project” under Section 3 of the Natural Gas Act. This authorization included natural gas processing, liquefaction and storage facilities at the LNG Terminal. These facilities included a fourth LNG storage tank and three liquefaction trains (Trains 1, 2, & 3) including the associated natural gas pre-treatment equipment, to produce up to 14.95 million metric tonnes per annum (MTPA) of LNG for export. The Liquefaction Project is currently under construction.

In this Sept. 28 application, Cameron LNG proposes to add additional storage and liquefaction facilities to the ongoing Liquefaction Project. The Expansion Project will include two additional liquefaction trains (Trains 4 and 5) each with a maximum LNG production capacity of 4.985 MTPA (9.97 MTPA total), and the associated natural gas pre-treatment facilities.

Cameron LNG is indirectly owned by affiliates of Sempra EnergyMitsui & Co. Ltd., Mitsubishi Corp. (through a related company jointly established with Nippon Yusen Kabushiki Kaisha), and Engie S.A., formerly GDF SUEZ S.A.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.