Apex works on 200-MW Blanco Canyon Wind Farm project in Texas

Sharyland Utilities LP filed with the Texas Public Utility Commission on Aug. 28 a Generation Interconnection Agreement with Old Settler Wind LLC for the 150-MW Blanco Canyon Wind Farm, which has a projected in-service date of Sept. 30, 2016.

The filing says that Apex Clean Energy Holdings LLC is the sole member of Old Settler Wind LLC. The filing said this project will share interconnection facilities with Cotton Plains Wind I LLC and that this project is located in the Electric Reliability Council of Texas region. The scheduled commercial operation date for the Blanco Canyon Wind Farm is Dec. 31, 2016.

The facility will be located in Floyd County, Texas, and interconnect at Sharyland’s White River Substation. It would consist of 63 wind turbines at 2.4 MW apiece.

Sharyland on Aug. 28 separately filed with the Texas commission a GIA with Cotton Plains Wind I, which is also an Apex company, for a 50-MW project, also called the Blanco Canyon Wind Farm. This project is scheduled for commercial operation on Dec. 31, 2016, and would consist of 21 General Electric wind turbines at 2.4 MW each.

Listed contacts for both development companies are Andrea Miller and Bill Pezalla out of Apex’s office in Charlottesville, Va., andrea.miller@apexcleanenergy.com and bill.pezalla@apexcleanenergy.com.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.