Hydro-Québec Distribution had a May 21 public opening for the bids received in response to its A/O 2015-01 call for tenders launched on March 4 for the purchase of 500 MW of firm capacity and associated energy to meet the long-term domestic electricity needs of its Québec customers.

Hydro-Québec Distribution said it received seven bids totaling 830 MW. The associated energy must be available for a minimum of 300 hours, mainly in winter months. The contracts will be over a twenty-year period, starting on the date of the beginning of deliveries, and the power must be available and guaranteed as of Dec. 1, 2018. However, a bidder could have submitted a proposal with deliveries starting after this date, by Dec. 1, 2019, at the latest.

This tender was issued to meet the very high demand during the winter peak period. Hydro-Québec will evaluate the bids and then announce which of them have been accepted. Once signed, the contracts must be approved by the Régie de l’énergie. Hydro-Québec has retained the services of Raymond Chabot Grant Thornton to assist in the tendering process and to act as its official representative.

The seven bids are from:

  • 8504792 Canada Inc., Varennes Renewable Energy Center, parent company York2York Energy Partners, interconnection in the Varennes municipality, 225 MW, guaranteed commencement date Dec. 1, 2018;
  • Boralex Inc., Cogen Kingsey Falls-25 MW, parent Boralex Inc., Kingsey Falls municipality, 25 MW, guaranteed commencement date Dec. 1, 2018;
  • Boralex Inc., Puissance Kingsey Falls-30 MW, parent Boralex Inc., Kingsey Falls municipality, 30 MW, guaranteed commencement date Dec. 1, 2018;
  • Énergie Brookfield Marketing S.E.C., Énergie La Lièvre, parent Brookfield Asset Management Inc., Gatineau et Bowman municipality, 50 MW, guaranteed commencement date Dec. 1, 2018;
  • Hydro-Québec Production, Système de puissance HQP, parent Hydro-Québec, Montréal municipality, 100 MW, guaranteed commencement date Dec. 1, 2018;
  • Hydro-Québec Production, Système de puissance HQP-2, parent Hydro-Québec, Montréal municipality, 200 MW, guaranteed commencement date Dec. 1, 2018; and
  • Hydro-Québec Production, Système de puissance HQP-3, parent Hydro-Québec, Montréal municipality, 200 MW, guaranteed commencement date Dec. 1, 2018.
About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.