800-MW Berks Hollow project advances in PJM queue process

Berks Hollow Energy Associates LLC has submitted a “Form of System Impact Study Agreement” to PJM Interconnection that outlines its plan to construct a 2×1 gas-fired combined cycle project with a total capability of 800 MW, said PJM in a study on the project dated March 2015.

This project would be on a property adjacent to the existing Ontelaunee 230-kV plant. The new units will be connected to the North Temple 230-kV substation by a single attachment line to be constructed by Berks Hollow Energy Associates. The proposed in-service date for this project, which is under PJM queue No. Z2-026, is June 1, 2018. The project entered the PJM queue system in February 2014.

This project would interconnect with the Metropolitan Edison system. It was studied as an 800 MW (Capacity 800 MW) injection at the North Temple 230-kV substation in the MetEd area. Z2-026 is a combined cycle facility which consists of one 390.5-MW steam turbine and two 228-MW combustion turbines.

This study is a mid-point in a PJM queue process that eventually leads to an Interconnection Service Agreement. The LS Power website shows this as an in-development project of 800 MW in size.

The Pennsylvania Department of Environmental Protection said in January 2014 that it had issued an air plan approval for an 855-MW, gas-fired power project in Berks County to Berks Hollow Energy Associates.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.