Southern California Ed files interconnect deals for 75 MW of solar projects

Southern California Edison filed with the Federal Energy Regulatory Commission on Dec. 4 four Small Generator Interconnection Agreements and four Service Agreements for Wholesale Distribution Service with four related solar photovoltaic project developers.

Those projects are:

  • SR Solis Vestal Herder LLC, 20 MW capacity, located at Ducor, Calif., to interconnect to SCE’s Vestal 66-kV Substation, commercial operation on Nov. 20, 2016;
  • SR Solis Vestal Almond LLC, 20 MW, Ducor, California, SCE’s Vestal 66-kV Substation, Nov. 20, 2016;
  • SR Solis Vestal Fireman LLC, 20 MW, Ducor, California, SCE’s Vestal 66-kV Substation, Nov. 20, 2016; and
  • SR Solis Crown LLC, 15 MW, Ducor, California, SCE’s Vestal 66-kV Substation, Nov. 20, 2016.

A project contact is: Josh Fields, Senior Development Manager, SolarReserve, Phone: 310-315-2200, Fax: 310-315-2201, 2425 Olympic Blvd., Suite 500 East, Santa Monica, CA 90404.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.