TERIC Power plans 2-MW gas-fired plant in Alberta

TERIC Power Ltd. filed a Nov. 10 application at the Alberta Utilities Commission for approval to construct and operate a 2-MW natural gas-fired power plant north of Hardisty, Alberta.

TERIC will install one induction-generating unit with a total real power generation capacity of 2 MW at the Sunrise project. The existing land use on the project site is the Killam 04-05-44-09-W4 Multi-well Gas Battery, an industrial facility owned and operated by TERIC Power. 

The Sunrise power plant’s fuel will be sweet natural gas withdrawn from the facility’s existing fuel gas headers. The expected in-service date for the power plant is Feb. 1, 2015.

A project contact is: Craig Barnes, TERIC Power Ltd., Phone: 403-660-5236, craig.barnes@tericpower.com.

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.