PJM Interconnection on July 11 filed with the Federal Energy Regulatory Commission an executed interconnection service agreement (ISA) among PJM, Public Service Electric and Gas as the transmission owner, and Public Service Electric and Gas as the developer of a 3.8-MW solar project.
The PSEG ISA facilitates the interconnection to the PJM transmission system of a 3.8-MW facility located in Sewell, New Jersey. The PSEG ISA indicates that PSEG shall have Capacity Interconnection Rights in the amount of 1.44 MW. Under the ISA, PSEG must on or before June 30, 2015, demonstrate commercial operation of all generating units.
This is the Beaverbrook (Kinsley Solar) project, located on Delsea Drive in Sewell.
A project contact is: Public Service Electric and Gas Co., 80 Park Plaza, T8, Newark, NJ 07102-4194, Attn: Albert Grisolia.