Entergy to Close, Decommission Vermont Yankee

NEW ORLEANS, Aug. 27, 2013 /PRNewswire/ — Entergy Corporation (NYSE: ETR) today said it plans to close and decommission its Vermont Yankee Nuclear Power Station in Vernon, Vt. The station is expected to cease power production after its current fuel cycle and move to safe shutdown in the fourth quarter of 2014. The station will remain under the oversight of the Nuclear Regulatory Commission throughout the decommissioning process.

“This was an agonizing decision and an extremely tough call for us,” said Leo Denault, Entergy’s chairman and chief executive officer. “Vermont Yankee has an immensely talented, dedicated and loyal workforce, and a solid base of support among many in the community. We recognize that closing the plant on this schedule was not the outcome they had hoped for, but we have reluctantly concluded that it is the appropriate action for us to take under the circumstances.”

Cheap natural gas, a high cost structure and “artificially low” energy and capacity prices in the region, led to the decision.

Entergy plans to recognize an after-tax impairment charge of approximately $181 million in the third quarter of 2013 related to the decision to shut down the plant at the end of this current operating cycle.

In addition to this initial charge, Entergy expects to recognize charges totaling approximately $55 to $60 million associated with future severance and employee retention costs through the end of next year. These charges will be classified as special items, and therefore, excluded from operational results.