CONSOL expects Bailey/Enlow Fork back at full speed by the end of August

CONSOL Energy (NYSE: CNX) said Aug. 9 that one of the two collapsed conveyor belts at its giant Bailey-Enlow Fork mine complex in southwest Pennsylvania should be returned to service the week of Aug. 19, which would allow this operation to work at 60% of capacity, with full production expected to resume by the end of August.

CONSOL had reported on July 30 that the prior weekend it had incurred a structural failure on its newly-installed above-ground conveyor system at the Bailey Preparation Plant, which processes coal for both Bailey and Enlow Fork, which are the two largest underground coal mines in the U.S. CONSOL said in the Aug. 9 update that it does not currently expect to curtail any domestic sales as a result of this incident.

This complex is a huge source of Pittsburgh-seam coal for both domestic and export markets. Bailey produced 5.9 million tons in the first half of this year and 10.8 million tons in all of 2011, while Enlow Fork produced 5.2 million tons in the first half and 10.2 million tons in 2011, according to U.S. Mine Safety and Health Administration data. Also, CONSOL is currently building the BMX project, which is basically a third longwall for Bailey that will add another 5 million tons per year of production at this complex.

Said CONSOL’s Feb. 10 annual Form 10-K report about belt installation work: “Construction of a new slope and overland belt at the Enlow Fork Mine in Pennsylvania began in 2010 and is expected to be completed by the end of 2013. Overland belt projects are expected to enhance safety, improve productivity, increase production and reduce costs. Modern conveyor systems typically provide high availability rates, thereby allowing mining equipment to produce at higher levels. Overland belts do not require the daily maintenance of the mine roof that underground haulage systems require allowing manpower to be reduced or redeployed to more productive work. Mine safety is expected to be enhanced by overland belts because older underground belt areas will be sealed. The total cost of the project is expected to be approximately $207 million of which approximately $28 million was incurred in 2011. As of December 31, 2011, total project-to-date expenditures were approximately $38 million.”

About Barry Cassell 20414 Articles
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy’s Coal Report. He was formerly with Coal Outlook for 15 years as the publication’s editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor’s degree from Central Michigan University.